POWER & ENERGY
Project case study
Client
Suzlon
Market / Industry
Power & Energy
Project
Rotor Realignment, North Brown Hill Wind Farm.
Description
MAX Services was engaged to complete a realignment of a turbine rotor at North Brown Hill Wind Farm in South Australia. The AC-500t crane was used in tandem with our 95t crane to tail the rotor.
The MAX team mobilised and lifted the load as safely and efficiently as possible, allowing the bolts to be changed so that the turbine could begin generating power again.