POWER & ENERGY

Project case study

Client

Mid North SA Wind Farm

Market / Industry

Power & Energy

Project

Wind Turbine Rotor Replacement

Description

The MAX Heavy Lift Team’s 500t Terex AC-500-2 mobile crane configured with sideways superlift and luffing jib (WIHISSL60°) was used to remove a 42t wind turbine rotor from a hub height of 80m to allow replacement of a wind turbine main bearing.

Our 200t Liebherr LTM1200-5.1 was used to assemble the 500t crane and assist with tailing the rotor. The photos show one of our Heavy Lift Team riggers installing the rotor lifting slings.

Call Now Button+61 8 8641 3955